London has 400 GW of grid requests holding up datacenter builds
lundi 10 février 2025, 11:28 , par TheRegister
And up to 70% of stalled energy generation projects are unlikely to be approved, claims regulator Ofgem
While the UK government wants to turbocharge datacenter construction, a newly published report says there are already 400 GW worth of outstanding requests for connection to the power grid around London, and regulator Ofgem estimates 60-70 percent of these will never happen.…